← Contents
Ch 6 of 25
Part One: The Machine · Chapter 6

Inertia, Voltage and Grid Strength

Spinning mass, fault current and reactive power, and what changes when generation sits behind inverters. The Iberian blackout of April 2025, and why the popular explanation for it was wrong twice over.

At 12:33 on the afternoon of Monday 28 April 2025, the Iberian Peninsula stopped. Three minutes earlier the Spanish system had been running normally, roughly 32 gigawatts of generation against about 25 gigawatts of demand on a mild spring day. Then, over a few seconds, something close to 15 gigawatts of generation disconnected itself. That is around 60% of what Spain was producing. Spain and Portugal went dark together, and 99% of Spanish demand was not restored until six the following morning.

Within hours the explanation had already been settled by people who had no data. There was a lot of solar on the system that lunchtime, and the grid had gone down, so the solar had done it. The more technical version of the same claim, which sounded better and was repeated by people who should have been more careful, was that the system had too little inertia: too few large spinning machines, too many inverters, not enough mechanical ballast to ride through a disturbance.

The final report of the ENTSO-E expert panel, published in March 2026 by a panel of 49 people drawn from transmission operators, regional coordination centres, ACER and national regulators, and chaired from two unaffected systems, found that neither of those was the cause. What it did find is more useful than the popular account, and the failure it describes is a market failure as much as an engineering one.

What actually happened

The panel identified at least fifteen contributing factors, which is itself the first lesson. What it describes is a combination: oscillations, both a local mode near 0.63 hertz and an inter-area mode near 0.2 hertz, together with gaps in voltage and reactive power control, inconsistent voltage regulation practice between operators, and rapid output reductions and generator disconnections inside Spain.

The mechanism that turned a manageable disturbance into a blackout was overvoltage, and it ran away from the system. Voltage began to rise. Generators, protecting themselves, disconnected. Each disconnection removed a machine that had been helping to hold voltage down, so the voltage rose further, which tripped more machines. Several of the actions taken to address what began as a small instability made it worse. That is a self-reinforcing loop, and once it is running there are seconds, not minutes, in which to stop it.

The plants that failed to hold voltage down were the conventional thermal ones. The panel found non-compliant reactive power control by exactly the machines whose job it was. Wind and solar did not cause the blackout, and the panel found they helped restore supply afterwards.

The president of ENTSO-E put the conclusion in one sentence: renewables were not the problem, voltage control was. And on the second, more sophisticated theory, the assessment of ENTSO-E and the Spanish system operator was that a lack of inertia was not a root cause either. The popular explanation was wrong twice, and the second error is the more instructive, because it was made by people who knew what inertia is.

Two different things the grid needs

The confusion is understandable, because a grid does need both of the things being discussed, and they are easy to run together. They are not the same, they fail on different timescales, and they are supplied by different equipment.

Table 6-1: Inertia and voltage support are different problems

 InertiaVoltage and reactive power
What it defendsFrequencyVoltage
Against whatA sudden mismatch between supply and demandToo much or too little reactive power on the network
TimescaleThe first seconds, before any control system actsContinuous, and local rather than system-wide
Where it comes fromRotating mass, or grid-forming inverters emulating itGenerator excitation, synchronous condensers, capacitors, reactors, inverters
Travels?Shared across the synchronous areaBarely. It has to be supplied near where it is needed

That last row is the one to hold on to. Frequency is a property of the whole synchronous area, so every machine in Europe sees the same frequency at the same moment and inertia anywhere helps everywhere. Voltage is local. Reactive power does not travel usefully over long distances, which means voltage support is not a commodity you can import from a neighbouring country when you need it. It has to exist near the problem, which means somebody has to have built it, and somebody has to be obliged to operate it correctly on an ordinary Monday when nothing appears to be wrong.

What inverters do change

None of this means the concern about inverter-based generation is invented. It is real, and Chapter 4 introduced the equipment. A synchronous machine is physically locked to the grid: it turns in step, and its stored kinetic energy is available to the system whether anyone planned for it or not. An inverter has no such property by default. It measures the grid and follows it.

A grid built mostly of followers has two genuine weaknesses. It has less inherent inertia, so frequency moves faster after a disturbance. And it supplies less fault current, which matters because protective relays were designed to detect a fault by the large current that flows into it. The engineering answers exist and are being deployed: synchronous condensers, which are essentially generators spun up with no fuel, purely to provide inertia and reactive power, and grid-forming inverters, which impose a voltage waveform rather than following one.

So the fragility argument survives the report. What does not survive is the specific claim that this event proves it. Iberia was not a demonstration that a renewable grid cannot hold together. It was a demonstration that a service which every textbook lists, which every grid code requires, and which barely anybody is paid properly to provide, will eventually not be provided.

Why this is a market chapter in disguise

Everything above is physics, which is why it sits in Part One. But the conclusion is economic, and it sets up Chapter 13.

Energy is easy to buy. It is measurable, it is fungible within a grid, and an exchange can clear it in five-minute intervals. Stability is a set of capabilities that must exist before they are needed, that produce nothing on the vast majority of days, and whose absence is invisible right up to the moment it is catastrophic. A market that pays only for megawatt-hours is paying for the one thing that is easy to measure and none of the things that keep the measurement possible.

Note also the two halves of what went wrong, because they fail independently. One is procurement: whether enough voltage support and reactive capability was contracted to exist at all. The other is compliance: whether the plants that had agreed to provide it actually did so on the day. The Iberian panel found a problem in the second, which no amount of additional procurement would have fixed. Chapter 13 takes up both, and Chapter 19 returns to the regulatory aftermath, because the durable consequence of 28 April 2025 is a set of new obligations.